How Much Does It Cost to Build a Pond in Texas?
Stock tank work in Texas averaged $167.59 an hour in AgriLife Extension’s 2026 custom rates survey. The most common rate was $200 an hour. For a whole job, a 2026 national cost guide puts a one-acre pond at $3,000 to $15,000. It puts a farm pond at $3,000 to $23,000.
These are market numbers, not our price list. A stock tank is the Texas word for a pond built to water livestock, and the same math prices both. For pond construction around Waxahachie, we look at the land and put the quote in writing.
What do published sources say a pond costs?
National cost guides price a pond mostly by its surface acres. Two 2026 guides give these ranges:
| Pond size or type | Published range | Source |
|---|---|---|
| 1/4 acre | $1,800 to $8,100 | 2026 national cost guide |
| 1/2 acre | $2,400 to $11,600 | Same guide |
| 1 acre | $3,000 to $15,000 | Same guide |
| 2 acres | $6,000 to $30,000 | Same guide |
| 4 acres | $12,000 to $60,000 | Same guide |
| Farm pond | $3,000 to $23,000 | Same guide |
| Farm pond | $3,750 to $13,000 | Second 2026 national cost guide |
| Large fishing pond or lake | $6,700 to $17,735 per acre | Second guide |
The first guide describes farm ponds as 1/4 acre to 5 acres and 6 to 12 feet deep. They have an earthen dam and a spillway.
Read the low ends with care. Rocky ground and a site that is hard to reach both cost more, the first guide says. Whether the dug dirt stays on site or gets hauled away also moves the price.
How is a stock tank priced in Texas?
AgriLife Extension surveys what Texas farms and ranches pay for custom work. Its 2026 report drew on answers from August through October 2025. Its line for stock tank construction and maintenance averaged $167.59 an hour statewide. That rate covers the machine with its operator and fuel.
Answers ran from $100 to $300 an hour. At the statewide average, every 10 machine hours comes to about $1,676.
| Unit | Published figure | Source |
|---|---|---|
| Machine hour, Texas stock tank work | $167.59 average, $100 to $300 range | AgriLife Extension 2026 survey, 27 answers |
| Cubic yard, digging a large pond | $1.50 to $4.00 | 2026 national cost guide |
| Soil report before building | $1,000 to $5,000 | Both national guides |
| Excavator project minimum | $500 to $800 | 2026 national cost guide |
The NRCS pond handbook says volume estimates for dams are made in cubic yards of earthfill in place. An acre-foot is one acre covered a foot deep, or 43,560 cubic feet. That is about 1,613 cubic yards. At the guide’s rates, each acre-foot of dug basin runs about $2,400 to $6,450.
What moves the number on a pond or stock tank?
Four parts of the job move the price: the dam, the clay, the spillway and the access. The NRCS pond handbook adds that good construction generally costs less in the long run than a dam built carelessly.
The dam and its core. On sloping ground, a stock tank holds water behind an earthen dam across a draw. The NRCS pond handbook shows a core trench cut down the dam’s center line. Its fill estimate adds the trench backfill and a settling allowance to the dam itself. That trench is excavation below the dam, and a taller dam takes more dirt.
The clay on site. A Texas extension soils paper rates the state’s soils for pond basins. More than 90 percent of Blackland Prairie soils had only slight to moderate limits for a pond. Even so, a thin layer of sand or gravel can cause serious seepage. Both national guides put a soil report at $1,000 to $5,000.
Black clay brings a catch of its own. The NRCS handbook warns that high-clay fill swells when wet and shrinks when dry. The shrinkage may open dangerous cracks. The handbook calls for fill in thin layers, each packed at near-optimum moisture.
The spillway and rock. A dam needs an auxiliary spillway, a path that carries storm runoff around it. The NRCS handbook warns a dam with too small a spillway will probably be destroyed in the first severe storm. Where water runs hard, rock rip rap for erosion control guards the spillway and the end of the dam.
Access and clearing. A site that trucks and machines struggle to reach costs more, the first guide says. The NRCS handbook has the dam site and the spillway site cleared of trees and brush first. For that part, see our guide to land clearing cost per acre.
Do you need a water right for a stock tank in Texas?
Texas Water Code Section 11.142(a) lets a person build a dam or reservoir on their own property without a permit. Normal storage must stay at 200 acre-feet or less, for domestic and livestock purposes. The exemption does not apply to a commercial operation. AgriLife Extension notes it is often called the stock tank exemption.
An acre-foot is about 325,851 gallons. A one-acre tank that averages 8 feet deep holds about 8 acre-feet. Using exempt water for another purpose, such as irrigating a cash crop, takes a permit under Section 11.143.
What are the dam rules for a pond in Texas?
The Texas Commission on Environmental Quality (TCEQ) runs the state’s Dam Safety Program. Its Chapter 299 rules apply to a dam taller than 6 feet with 50 acre-feet or more of maximum storage. They also apply to a dam 25 feet or taller with 15 acre-feet or more. A high or significant hazard dam over 6 feet counts too.
Hazard turns on what sits below the dam. In TCEQ’s guidance, a low hazard dam has no permanent homes where a breach would flood.
Texas Water Code Section 12.052 exempts some dams on private property from safety requirements. A dam qualifies when it meets four tests:
- It holds less than 500 acre-feet at maximum capacity.
- Its hazard rating is low or significant.
- Its county has fewer than 350,000 people.
- It sits outside city limits.
TCEQ posts a map of the counties that qualify. Ellis County, at 192,455 people in the 2020 Census, is under that line. Exempt dam owners still have to meet the state’s operation and maintenance requirements. Whatever the dam, Texas law requires a call to 811 at least two business days before digging.
Can NRCS help pay for a stock tank?
It can be worth asking. NRCS’s Environmental Quality Incentives Program (EQIP) gives financial and technical help to agricultural producers and non-industrial forest managers. Applications come in all year, but each funding cycle has state ranking dates. The local USDA service center starts the application.
The Texas State Soil and Water Conservation Board runs a cost share route through local soil and water conservation districts. Its fiscal 2027 practice list allows pond cost share only when sound grazing management needs one. Ask before the work is scheduled, since each program sets its own rules.
How do you get a real number for your pond?
Published ranges show the scale. The number for your pond comes from the land: the draw, the clay, the spillway route and the way in. We look at the land and put the quote in writing. See how we build stock tanks and ponds, or call or text (469) 309-7002.